Our Projects.

Meadow Lane Southport

Client: Barnfield Construction 

Cost: £1,000,000.00 (plant & labour project)

Scope:47 houses, all substructure works, roads & sewers (100m long culvert)

Status: Ongoing. Completion forecast for June 2022.

Aftercare Facility - Miller Road, Preston

Client: Seddon 

Cost: £700,000.00

Scope: Carehome facility

Status: Started June 2022.. Ongoing.

Miller Road Preston

Client: Seddon Construction 

Cost: £600,000.00

Scope: Roads & sewers 

Status: Forecast to finish roads & sewers August 2022.

Hare Hill Road, Hyde

Client: Equans 

Cost: £1,750,000.00

Scope: Roads, sewers, plots up to finish floors

Status: Started June 2022. Ongoing.

Upcoming Projects

STEN has many potential projects coming soon. Our upcoming projects will be listed below in due time.

Plots - Miller Road, Preston

Client: Seddon 

Cost: £1.900,000.00

Scope: 78 Plots

Status: Starting July 2022.

Completed Projects

Our completed projects are listed below.

Royal Oldham Hospital

Client: Engie 

Cost: £500,000.00 

Scope: New hospital wing, including hard landscaping, drainage, sewers.

Status: Completed 2021.

Royal Lytham Golf Club

Client: Royal Lytham Golf Club

Cost: £50,000.00 TBC

Scope: Refurbishment to two car parks.

Status: Ongoing.

Wellington Street

Client: Lane End

Cost: £450,000.00

Scope: work done regarding St Bedes college, including landscaping and drainage.

Status: Finished 2019.

The Strand, Liverpool

Client: SSC Contractors

Cost: £400,000

Scope: Groundwork regarding a new apartment, including hard landscaping, drainage, sewers, plot work in the Liverpool area.

Status: Finished 2018.

Abbey Road, Sandbach

Client: Lane End Developments

Cost: £1,250,000.00

Scope: 180 new houses, including hard landscaping, drainage, sewers.

Status: Phase 2 ongoing.

Mark Rake

Client: Lane End

Cost: £375,000.00

Scope: New apartment block and houses, including Roads and Sewers, Plot works, Drainage and Hard Landscaping.

Status: Finished 2018.

Merrion Way, Leeds

Client: SSC Contractors

Cost: £400,000

Scope: student accommodation in the Leeds area, including plot work, drainage, hard landscaping and sewers.

Status: Finished 2018.

Hawthorne St, Warrington

Client: Mulbury Homes

Cost: £1,000,000.00 TBC

Scope: 50 new houses including hard landscaping, drainage, sewers.

Status: On hold. Developer into receivership.

Bradshaw Street, Wigan

Client: Lane End Developments

Cost: £700,000.00

Scope: 50 new houses, including hard landscaping, drainage, sewers.

Status: Just completed early 2020.

Beech Tree

Client: Lane End Developments

Cost: £1,000,000.00

Scope: New apartment block and houses, including Roads and Sewers, Plot works, Drainage and Hard Landscaping.

Status: Finished 2019.

Edge Fold Road

Client: Lane End Developments

Cost: £850,000.00

Scope: New houses, including plot work, drainage, hard landscaping and sewers.

Status: Finished 2019.

Hazel Grove, Stockport

Client: Mulbury Homes

Cost: £1,850,000.00 TBC

Scope: 60 new houses and 1 apartment block including hard landscaping, drainage, sewers.

Status: On hold. Developer into receivership.

Fairfield Nursery

Client: Fox Brothers

Cost: £80,000.00

Scope: New houses, including Roads and Sewers, Plot works, Drainage and Hard Landscaping in the Poulton Le Fylde area.

Status: Finished 2018.

Marsh Mill Tavern

Client: Fox Brothers

Cost: £40,000.00

Scope: Extension to pub car park.

Status: Finished 2019.

Charles Street

Client: CPUK 

Cost: £1,000,000.00

Scope: New Housing Estate including Roads and Sewers, Plot works, Drainage and Hard Landscaping.

Status: Finished 2018.

Bowness Road, Middleton

Client: Engie 

Cost: £2,800,000.00 

Scope: 49 new houses including roads, hard landscaping, drainage, sewers. 

Status: Completed and handed over.

Lucy Street

Client: Lane End

Cost: £400,000.00

Scope: 36 new houses, including Roads and Sewers, Plot works, Drainage and Hard Landscaping.

Status: Finished 2019.

Hare Hill Road (enabling)

Client: Equans 

Cost: £40,000.00

Scope: Enabling works for compound & car parking.

Status: Completed